电缆支架安装的要点

2017/06/26  浏览次数:

  电缆支架安装的要点:

  Main points of installation of cable support:

  1、 安装前,电缆沟道清理干净;找出予埋扁铁并符合设计。

  1. Clean the cable channel before installation. Find the buried flat iron and conform to the design.

  2 、将符合设计、规格型号的支架运往现场,无显著扭曲、变形、油漆完整。

  2, the design, specifications, models of the stent shipped to the scene, no significant distortion, deformation, paint integrity.

  3、 按图纸设计的标高,先安装两端支架,在两端支架上下层各拉一线绳,找出同一标高,再安装中间支架。

  3, according to the design elevation, first installed at both ends of the bracket bracket at both ends, the lower pull a string, find the same elevation, and then install the middle bracket.

  4、 按设计要求安装电缆支架,固定牢固,横平竖直。

  4 、 according to the design requirements, install the cable bracket, fixed firmly, vertical and horizontal.

  5、电缆支架安装时,上层横撑至沟顶距离≥150mm-200mm;下层横撑至沟底距离≥50mm-100mm。

  5, the cable bracket is installed, the upper brace to ditch the top distance is greater than or equal to 150mm-200mm; the lower transverse bracing to the ditch bottom distance of more than 50mm-100mm.

  6、 电缆支架安装后,水平高低偏差≤5mm;垂直左右偏差≤5mm。

  6, after the installation of cable support, the level of deviation is not greater than 5mm; the vertical deviation is not greater than about 5mm.

  7、 在有坡度的电缆沟或构筑物上安装支架时,与电缆沟或构筑物同坡度布置。

  7, in the slope of the cable trench or structure on the installation of stents, and cable trench or structure with the slope layout.

  8、 电缆支架应与接地网有≥2个明显的接地点并可靠连接。

  8, with more than 2 cable support should be obvious and reliable connection and grounding grounding.

  9、支架安装完后,除去焊渣,做防锈处理。

  9, after the stent is installed, remove welding slag and do rust prevention.

  • 山东久丰伟业不锈钢工程有限公司  联系人:刘经理; 
  • 电话:0531-88606796; 传真:0531-88601877
  • 手机:15589928777;   网址:www.sdjfwy.cn    
  • 地址:济南市历城区工业北路159-19号
  • 技术支持:企力网一站式网络营销推广方案
  • 备案号:鲁ICP备16041896号-2
  • 网站地图 /XML地图
网站声明:

本站部分素材搜集来源网络,如内容有侵权,请联系我司立即删除!本站内容按照相关法律法规进行编写;如有不当请联系我司立即删除!

在线客服